A subpanel is a secondary electrical distribution panel that is fed from the home’s main service panel to provide additional circuit capacity or to serve a remote area of the house or property. Technically, a subpanel contains breakers that control branch circuits just like the main panel, but it is connected to the main by a feeder (two hot legs, a neutral, and a grounding conductor). Unlike the main service panel, the subpanel does not have the service disconnect; it must have the neutral bus isolated from the equipment grounding bus so fault currents follow the grounding conductor back to the service. Proper feeder sizing, breaker ratings, and grounding/neutral separation are essential to meet NEC and local code requirements.

A new home typically needs a subpanel when the planned electrical load or layout exceeds what your main panel can reasonably accommodate. Common triggers include large or spread-out floor plans, detached garages or workshops, accessory dwelling units, dedicated circuits for EV chargers, hot tubs, electric heating or multiple high-demand appliances, and long cable runs where voltage drop becomes a concern. The decision is based on a formal load calculation done by a licensed electrician and influenced by future-proofing goals; for example, planning for a level 2 EV charger or an all-electric kitchen often pushes a design toward additional subpanel capacity. Permits and inspections are required, and local code and utility rules can affect feeder sizing, ampacity, and allowable configurations.

At RKM Homes we coordinate electrical planning early in the design so panel capacity and placement are integrated with the house layout and your long-term needs. Our standard approach is to work with a licensed electrician to size the service and any required subpanels, specify feeder conductor sizes and conduit runs, and locate panels for accessibility and efficient routing to high-demand areas like garages, mechanical rooms or ADUs. This upfront planning minimizes change orders during construction, ensures compliance with Denver-area codes and inspections, and leaves room for future upgrades such as EV charging, battery storage, or additional living spaces.

 

What’s the difference between a main panel and a subpanel — and when does a new home need a subpanel?

As a custom home builder I explain this to clients all the time: the main panel is the house’s primary service distribution point where the utility feed, meter/disconnect and the main breaker are located. A subpanel is simply a secondary breaker box fed from the main that serves a specific area or group of loads. Functionally they both hold breakers and distribute circuits, but a subpanel is used to localize circuit distribution so you don’t have long runs of cable back to the main and so you can add circuits in a single, convenient place.

You’ll typically choose a subpanel in a new home when you have a cluster of loads in a separate area or when distance makes it impractical to run many individual circuits back to the main. Common examples on our builds are a garage or detached shop, an ADU or guest suite, a second-floor mechanical/lighting package, a dedicated EV charger/workshop area, or when a renovation adds many new circuits. Putting a subpanel close to the loads simplifies wiring, reduces conduit and trenching costs (for detached structures), and makes future expansion cleaner and less disruptive.

Practical steps I recommend: plan for any likely subpanels during the design phase so conduit, framing space and routing are accounted for — it’s far cheaper than cutting into finished walls later. Decide now which zones might need concentrated circuits (garage, basement shop, ADU, major appliances) and discuss locations with your electrician so breaker space and access meet your needs. Finally, treat the subpanel installation as part of the electrical scope handled by a licensed electrician; it will be sized and configured to match your service and to make future changes straightforward.

 

 

 

How do I size a subpanel and calculate feeder amperage for my new custom home?

Start by building a realistic electrical inventory: list every major appliance, HVAC/heat pump, electric water heater, EV charger, dryer, well pump, and any dedicated circuits for a workshop or future additions. Each of those loads has a starting/continuous amp draw and some are considered continuous loads (circuits that run 3 hours or more) which must be sized at 125% when selecting feeder ampacity. On our projects we collect nameplate ratings and expected simultaneous use for each space so the electrician can run a formal load calculation — the result tells you the minimum feeder amperage and whether a separate subpanel is needed for a garage, ADU, or high-demand zone.

For practical planning, use common subpanel sizes as a rule of thumb: 60 A, 100 A, and 125 A are typical for residential subpanels. A useful contractor-level guideline is that a 60 A subpanel is usually fed with #6 copper, a 100 A subpanel with #3 copper, and a 125 A subpanel with #1 copper (aluminum conductors require larger sizes). If you’re planning an EV charger (40–60 A), a second HVAC unit, or a large shop with air compressors, bump the subpanel size accordingly — for example, a garage subpanel serving an EV charger and a 240V shop circuit will often be 100 A or larger.

From a builder’s perspective, don’t guess at future needs — oversize modestly where conduit and breaker space are cheap compared with retrofitting later. Provide your electrician with the inventory and any future plans (EVs, hot tub, finished basement) early in design so the feeder and subpanel can be sized once and done right. We also recommend asking the electrician for a written load calculation and a spare capacity target (commonly 20–30% spare) so you have a clear, verifiable basis for the feeder ampacity and panel selection when the permit reviewer asks.

 

How should grounding and bonding be handled in a subpanel for my new home?

When we install a subpanel in a new custom home, the most important rule we follow is: keep neutrals and grounds separate. The neutral (grounded) conductor is bonded to the service disconnect at the main panel only; in the subpanel the neutral bus must be electrically isolated from the metal enclosure. The grounding conductors (equipment grounds) are tied to a separate grounding bus that is bonded to the panel enclosure. On the job this looks like an isolated neutral bus with plastic or nylon standoffs and a clearly bolted grounding bus or bonding screw — ask your electrician to point these out before drywall goes up.

A proper feeder to a subpanel is four conductors: two hots, one insulated neutral, and one equipment grounding conductor. For detached structures we also install a local grounding electrode system (ground rod(s)) and bond that electrode system to the grounding conductor at the subpanel; neutrals still stay isolated there. Never allow a neutral-to-ground bonding jumper at a subpanel inside the same building as the main service — that creates parallel neutral return paths on grounding conductors, which can energize metal parts and create shock and interference problems. The specific sizes of the grounding and feeder conductors are picked by the electrician to match the breaker and run length; for homeowners it’s reasonable to ask for the ampacity of the feeder and the wire sizes that will be used.

Practical steps you can take: during the design and rough-in ask your builder or electrician to label the main panel as the single neutral-ground bond location and to label any subpanel “Neutrals must remain isolated.” Request a four-conductor feeder and, if the subpanel will be in a detached garage or shop, confirm a grounding electrode will be installed and bonded. Finally, require permits and inspection — the inspector will verify neutral separation, bonding, and conductor sizing; having those checks on the schedule prevents rework and protects your family and equipment.

 

Where should I place a subpanel in my new home and how do I route the feeder?

When we set the electrical layout on a custom home, we place subpanels near the loads they will serve — common spots are garages for EV chargers and workshop circuits, mechanical rooms for HVAC and water heaters, and basements for finished basements or accessory living spaces. Avoid locating a subpanel inside bedroom closets or bathrooms and plan for a clear working space roughly 30 inches wide and about 3 feet out from the panel with comfortable headroom (roughly 6½ feet); keeping it in a utility area makes future access, labeling, and maintenance much easier. Also leave room around the panel for expansion — mounting it where additional breakers or a larger subpanel can be fitted later saves cutting drywall and relocating finishes down the road.

Feeder routing should be as direct and short as practical to reduce installation complexity and voltage drop. We prefer runs through basements, utility chases or attics rather than across finished living areas — that minimizes drywall repairs and keeps the feeder accessible for future work. If you need an underground run to a detached garage or exterior panel, plan the trench and conduit path early in the site work phase so the electrician can pull conductors in conduit rather than trying to fish through finished framing later.

Physical constraints of the structure influence placement: avoid cutting large notches or holes through load-bearing joists and coordinate with framing so the panel can be mounted on a full stud wall or blocking is installed, not just drywall. Route feeders to avoid heat sources, sharp bends, and places where they’d need additional protection (e.g., where they run low and could be damaged). We always coordinate panel location with rough‑in trades so plumbing, HVAC ducts, and gas lines don’t conflict with the chosen route and so conduit or cable paths are left accessible for the electrician to complete the final connection.

 

 

Do I need permits, inspections, and a licensed electrician to put a subpanel in my new Denver home?

As a Denver custom home builder I always treat a subpanel installation as a permitted electrical change — and you should, too. The city and county require a permit so the work can be inspected at rough and final stages; the permit application typically lists the electrician and the panel location/ampacity. Before work starts, ask your builder or electrician for the permit number and the name on the permit so you can verify it with the local building department; having that verified up front prevents surprises during framing or drywall inspections.

Inspectors will look for things that affect safety and final meter release: correct breaker sizing and labeling, clearance and working space around the panel, proper feeder terminations, conduit and conduit fill where required, and that neutrals and grounds are handled per code at the subpanel. Expect at least two inspections — a rough inspection before drywall/electrical cover and a final inspection after the panel is energized — and plan for short re-inspections if the inspector notes corrections (common items are missing labels, undersized conductors, or improper bonding). Coordinate scheduling with your electrician and the utility for meter setting; missed coordination is a leading cause of project delays.

Hire a licensed, insured electrician who will legally pull the permit and sign the work off. In Colorado you should ask for the contractor’s license number, proof of liability insurance and workers’ comp, and a copy of the final inspection or certificate of compliance when the job is done. Keep the permit documentation, final inspection card, and an as-built breaker schedule in your home file — lenders, insurers, and future buyers will expect to see signed-off electrical work, and unpermitted or uncertified subpanels can cost time and money to remediate.